Good morning. Fyi, (From the Onsite Coordinator)
Building # 1750 100% done.This week we are working on Building # 1350 and 1450, back and front railings. Buildings # 1500 & 1200 front railings are 100% done. We expect to paint upstairs railings next week. Doors front @ units # 1351, 1506 & 1507 still pending to be painted.
If you all have any questions please let me know. I understand this it a hard project to manage with all the owners but we are all doing our best and I really appreciate your cooperation !