February 2020 Interior Termite Inspection Update

Good Morning All,

It is that time again we are starting the interior termite inspections I have two scheduled for February.  I will keep you all posted as soon as I get each building scheduled.

 

Building 1750 2/4/2020 at 8:30am

 

Building 1850 2/18/2020 at 8:30am

 

(ADDITION TO FEB SCHEDULE) Building 1550 2/27/2020 at 8:30am

If you all have any questions please let me know.  Email is the best way to contact me !

Chris@coastalrealtyfl.com

 

Replacement of Divider Fences

Hardwick Fence is starting today at 1603 on the divider fences in the back of units.  They will be working for at least 5 to 6 days to replace the rest.  I just wanted you all to know so that you wont get startled.  I can’t at this time give you an exact date for every install as it will certainly depend on weather and the time it takes to do each one.

 

If anyone has any questions please let me know !

Chris Haga

January 21, 2020  Board Meeting Notes

There were 7 owners in attendance at the meeting.

In addition to the published Agenda, owners comments included:

  • Concerns regarding owners / tenants not complying with direction regarding projects.
  • Communication from Management

Official meeting minutes will be posted on our website after approval at the next Board Meeting.

Thank you all ! 

Chris 

PET REMINDERS

Good Morning All,

This is a reminder that if you have a pet, please make sure that they are NOT left out on balconies unattended.

I have had a few complaints about constant barking, so please be respectful of your neighbors and make all efforts to keep your dog from barking.  It seems to be early in the morning and in the evening when folks are trying to sleep.

Thank you in advance for your assistance with this.  If you have any questions please feel free to contact me !

Christine (Chris) M. Haga
Association Manager – CAM
Coastal Realty & Property Management, Inc.
904-471-6606 Ext 108
904-471-2866 Fax
Chris@CoastalRealtyfl.com

Painting Update

Good morning. Fyi,  (From the Onsite Coordinator)

Building # 1750 100% done.This week we are working on Building # 1350 and 1450, back and front railings. Buildings # 1500 & 1200 front railings are 100% done. We expect to paint upstairs railings next week. Doors front @ units # 1351, 1506 & 1507 still pending to be painted.

If you all have any questions please let me know.  I understand this it a hard project to manage with all the owners but we are all doing our best and I really appreciate your cooperation !